Mandela National Stadium (Namboole) renovation
A five-year rebuild has returned Namboole to international standard, though work continues ahead of Uganda's 2027 AFCON co-hosting.
Delivered by UPDF Engineering Brigade, shared for context. This is not an NPPU-procured project.
Namboole, formally the Nelson Mandela National Stadium, was built in 1997 with a $36 million Chinese grant and hosted the national football team for two decades before it was closed in 2019 and blacklisted by CAF in 2020 over substandard facilities.
A rebuild led by the UPDF Engineering Brigade began in 2022, adding permanent seating, new dressing rooms, a scoreboard and refreshed floodlights, at a cost of about 97 billion Ugandan shillings for the works carried out between 2019 and 2024.
The stadium reopened in 2024 with a reduced all-seater capacity of about 38,000 in time to host matches at the CHAN 2024 tournament, though further work on the stadium's roof and facade has continued since, as part of preparations for Uganda's co-hosting of the 2027 Africa Cup of Nations.